A project team is deciding on whether to "make or buy". As part of the decision-making process, the team decides to request a product update from key product suppliers. Which of the following should be used to facilitate this?

A. RFQ
B. RFI
C. RFP
D. Vendor selection

Answer: B


Which of the following is typically the LAST step when acquiring a product or service from a vendor?


A. Vendor selection
B. Evaluate seller response
C. Contract development
D. Contract signing

Answer: D