Which of the following is BEST suited for assigning resources to WBS tasks?
A. WBS defines functional teams which should then be mapped to project scope items
B. WBS contains the project schedule which should be used to determine timing of when to engage functional teams
C. WBS defines the description of the end result delivered by the project
D. WBS defines activities and deliverables that can be mapped to functional teams
Answer: D
Which of the following can be used as a quality metric when performing quality planning?
A. Quality control
B. Cost benefit analysis
C. Perform preventative actions
D. Quality assurance
Answer: B