Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?
A. AON
B. PERT
C. CPM
D. GERT
Answer: C
A draft structure for a risk tracking sheet has been provided below:
1. Risk identifier
2. Risk status
3. Risk description
4. Mitigation steps
5. Mitigation status
Which of the following should be ADDED to the risk tracking sheet?
A. Risk rating
B. Stakeholder risk tolerance
C. Revised project schedule
D. Risk matrix
Answer: A