Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?

A. AON
B. PERT
C. CPM
D. GERT

Answer: C


A draft structure for a risk tracking sheet has been provided below:

1. Risk identifier
2. Risk status
3. Risk description
4. Mitigation steps
5. Mitigation status

Which of the following should be ADDED to the risk tracking sheet?

A. Risk rating
B. Stakeholder risk tolerance
C. Revised project schedule
D. Risk matrix

Answer: A