Which of the following should be used when determining the details of a project component or scope entry?

A. WBS Dictionary
B. Project Management Plan
C. Work Breakdown Structure
D. Project Charter

Answer: A


During the course of a project, key stakeholders have requested new requirements after the business requirements document has already been signed off. Which of the following should have been performed earlier in the project in order to deal with this situation?

A. Ensure that stakeholders understand that once requirements are approved the scope cannot be changed.
B. Develop a clear communications flow between the project and business stakeholders.
C. Perform multiple rounds of requirements solicitation before permanently locking down the scope.
D. Agree on a process to deal with project change requests.

Answer: D