A project team member, Joe, has completed his project work. Although the project is not completed yet, Joe has been assigned by the PMO director to a new project. Which of the following describes the organization structure Joe works in?

A. Functional
B. Matrix
C. Project based
D. Strong Matrix

Answer: C