Pass4sure PK0-003 Question Answer

A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE about this scenario?  

A. The new piece of software will most likely expand the scope of the project therefore a new scope statement must be written.
B. The current project must be completed and a new project can be started to implement the additional software.
C. Quality management metrics are affected therefore the project manager should review the quality of the project.
D. Project schedule may be affected and the project manager must follow the change control process.

Answer: D



While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitting a change control form?

A. Consult the project sponsor
B. Identify the change
C. Perform a feasibility study
D. Perform impact analysis

Answer: B