A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the following should be done NEXT?

A. Implement the change
B. Update the change registry
C. Document the change
D. Perform an impact analysis

Answer: D                                                     


Additional company employees have been assigned to the project. Which of the following will be affected? 

A. The timeline may be positively affected at the expense of the project cost.
B. This change does not affect the triple constraint because the additional employees are already on the company payroll.
C. The quality of the product will improve but it will add more time to the project to train the new employees.
D. Total project cost will be reduced because the project can now be completed sooner.

Answer: A