Thursday 28 January 2016

Pass4sure PK0-003 Question Answer

One of the MAIN purposes of a kick-off meeting is to:

A. Assign and review roles and responsibilities to the project team.
B. Allow the project sponsor to introduce the project manager to the team.
C. Review the project definition document and make the appropriate changes.
D. Ensure project team members communicate amongst each others.

Answer: A                                                       

After the ground breaking at a new construction site, the pile driving operation comes to a full stop due to the nature of the terrain. Which of the following is MOST likely to occur?

A. The project communication plan must be updated and a stakeholder meeting must be scheduled.
B. The project manager must manage the new issue as the project schedule could be delayed.
C. The project manager must implement conflict resolution and review the resource requirement.
D. The project scope statement must be reviewed and the project manager must prepare a performance report.

Answer: B