Which of the following MUST be clearly defined in a project charter? 

A. Quality
B. Scope
C. Action items
D. WBS

Answer: B


Which of the following is used to provide a functional description of the efforts which are required in order to accomplish a task?

A. Gantt chart
B. PERT
C. GERT
D. WBS dictionary

Answer: D