Which of the following is used to provide a functional description of the efforts which are required in order to accomplish a task? 

A. Gantt chart
B. PERT
C. GERT
D. WBS dictionary

Answer: D


A project manager is entering the list of a project’s activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the following is the project manager building? 

A. Gantt chart
B. Work Breakdown Structure
C. Critical Path
D. PERT chart

Answer: A