Question: 1

A project manager is completing a project schedule network diagram using dummy activities to show all logical relationships. Which of the following tools is the project manager using?
A. ADM
B. WBS
C. AON
D. PDM

Answer: A


Question: 2

Which of the following would be the benefit of saving a project binder in a centralized location?
A. Provides an opportunity for another project manager to review the binder and make corrections.
B. Provides an opportunity for team members to review their contributions.
C. Provides other project managers the opportunity to review the project information.
D. Provides stakeholders the opportunity to modify the change request forms.

Answer: B